‘In February 2018 (week 45) a major signalling commissioning was successfully delivered by Crossrail Anglia. Vertex supported the Principal Contractor, Costain with Signalling Engineering Management resource to ensure that all supporting deliverables were in place. A series of enabling works stages were successfully delivered in the lead up to this major commissioning with Vertex CSM and Engineering Management support.
A key package within this major commissioning was the bringing into use of the completely rebuilt and upgraded Gidea Park Sidings. Vertex delivered a timely CSM SAR sign-off to allow the integrated multi-discipline design to be implemented working closely with the Costain Engineering Management team. These fully signalled, remodelled and wired sidings were commissioned successfully.’